PROJECT DETAILS


IMPLEMENTING AGENCY : Local Government Engineering Department
PROJECT CODE : 5069
NAME OF PROJECT : Begum Rokeya Srity Kendra connecting Rural Infrastructure Development Project
APPROVAL STATUS : Approve DATE OF APPROVAL:
2013-02-28
NAME OF PD : Faruk Ahmed
OBJECTIVES 1 :
OBJECTIVES 2 :
OBJECTIVES 3 :
PROJECT LOCATION : Rangpur
REPORTING PERIOD : 2013-01-01 to 2015-06-30
STARTING DATE : 2013-01-01 COMPLETION DATE : 2015-06-30
FINANCIAL YEAR : 2013 SOURCE OF FUND : GOB
: TOTAL GOB PA
PROJECT COST : 1700 1700 0
FINANCIAL INFORMATION
: TOTAL GOB PA
ADP ALLOCATION : 600 600 0
ADP RELEASE : 450 450 0
ADP EXPENDITURE : 449 449 0
RADP ALLOCATION : 0 0 0
RADP RELEASE : 0 0 0
RADP EXPENDITURE : 0 0 0
CUMULATIVE EXPENDITURE : 449 PHYSICAL PROGRESS : 35 %
COMMENTS :

Khandker Mosharraf Hossain

Abdul Malek

Last Update Date

2017-11-23