::LGD::

PROJECT DETAILS


IMPLEMENTING AGENCY : Local Government Engineering Department
PROJECT CODE : 5073
NAME OF PROJECT : Northern Bangladesh Integrated Development Project
APPROVAL STATUS : Approve DATE OF APPROVAL:
2013-03-05
NAME OF PD :
OBJECTIVES 1 :
OBJECTIVES 2 :
OBJECTIVES 3 :
PROJECT LOCATION :
REPORTING PERIOD : 2013-03-01 to 2019-06-30
STARTING DATE : 2013-03-01 COMPLETION DATE : 2019-06-30
FINANCIAL YEAR : 2013 SOURCE OF FUND : GOB
: TOTAL GOB PA
PROJECT COST : 270594 57837 212757
FINANCIAL INFORMATION
: TOTAL GOB PA
ADP ALLOCATION : 3848 800 3848
ADP RELEASE : 405 405 0
ADP EXPENDITURE : 332 332 0
RADP ALLOCATION : 0 0 0
RADP RELEASE : 0 0 0
RADP EXPENDITURE : 0 0 0
CUMULATIVE EXPENDITURE : 346 PHYSICAL PROGRESS : 0 %
COMMENTS :