PROJECT DETAILS


IMPLEMENTING AGENCY : Dhaka WASA
PROJECT CODE :
NAME OF PROJECT : Well Filled Construction Project at Tetulzhora-Bhakurta area of Saver Upazila (Part-2)
APPROVAL STATUS : Approve DATE OF APPROVAL:
0000-00-00
NAME OF PD : Mohd. Akhtaruzzaman
OBJECTIVES 1 : To Supply 150 MLD safe water for immediate supplement to city water supply from Tetulzhora-Bhakurta area of Saver Upazila at Gabtoli, Mirpur point from Construction Well Field
OBJECTIVES 2 :
OBJECTIVES 3 :
PROJECT LOCATION : Saver Upazila
REPORTING PERIOD : 2012-07-01 to 2016-06-30
STARTING DATE : 2012-07-01 COMPLETION DATE : 2016-06-30
FINANCIAL YEAR : 2013 SOURCE OF FUND : GOB, South Kore
: TOTAL GOB PA
PROJECT COST : 52100 14200 36900
FINANCIAL INFORMATION
: TOTAL GOB PA
ADP ALLOCATION : 12000 3000 9000
ADP RELEASE : 0 0 0
ADP EXPENDITURE : 326 326 0
RADP ALLOCATION : 0 0 0
RADP RELEASE : 0 0 0
RADP EXPENDITURE : 0 0 0
CUMULATIVE EXPENDITURE : 635 PHYSICAL PROGRESS : 2 %
COMMENTS :

Khandker Mosharraf Hossain

Abdul Malek

Last Update Date

2017-12-18