::LGD::

PROJECT DETAILS


IMPLEMENTING AGENCY : Dhaka WASA
PROJECT CODE :
NAME OF PROJECT : Interim Period Emergency construction and rehabilitation of Sewerage Line Project-2
APPROVAL STATUS : Approve DATE OF APPROVAL:
2010-07-20
NAME OF PD : Md. Mosfiqur Rahman
OBJECTIVES 1 : Swerage Line rehalitation and reconstruction
OBJECTIVES 2 : To keep Polution free Environment by removing Swerage overflow through Re-construction/ Rehabilitation of two swerage lift pump station
OBJECTIVES 3 :
PROJECT LOCATION : Dhaka City
REPORTING PERIOD : 2010-07-01 to 2014-06-30
STARTING DATE : 2010-07-01 COMPLETION DATE : 2014-06-30
FINANCIAL YEAR : 2013 SOURCE OF FUND : GOB
: TOTAL GOB PA
PROJECT COST : 9143 8643 0
FINANCIAL INFORMATION
: TOTAL GOB PA
ADP ALLOCATION : 2500 2500 0
ADP RELEASE : 0 0 0
ADP EXPENDITURE : 77 77 0
RADP ALLOCATION : 0 0 0
RADP RELEASE : 0 0 0
RADP EXPENDITURE : 0 0 0
CUMULATIVE EXPENDITURE : 3400 PHYSICAL PROGRESS : 60 %
COMMENTS :

Khandker Mosharraf Hossain

Abdul Malek

Last Update Date

2017-12-18