IMPLEMENTING AGENCY : Dhaka WASA
PROJECT CODE : 8487
NAME OF PROJECT : Dhaka Water Supply and Sanitation Project.
APPROVAL STATUS : Approve DATE OF APPROVAL:
2008-10-23
NAME OF PD : Md. Abul Kashem
OBJECTIVES 1 : •The project objective is to improve the sustainable delivery of storm water drainage, wastewater disposal from the city.
OBJECTIVES 2 : •Water supply to the low income community living in and around the city by the DWASA to the population of Dhaka city
OBJECTIVES 3 :
PROJECT LOCATION : Greater Dhaka City.
REPORTING PERIOD : 2008-11-01 to 2014-06-30
STARTING DATE : 2008-11-01 COMPLETION DATE : 2014-06-30
FINANCIAL YEAR : 2013 SOURCE OF FUND : GOB and World B
: TOTAL GOB PA
PROJECT COST : 116017 11712 104305
FINANCIAL INFORMATION
: TOTAL GOB PA
ADP ALLOCATION : 15600 600 15000
ADP RELEASE : 5086 0 5086
ADP EXPENDITURE : 589 0 589
RADP ALLOCATION : 0 0 0
RADP RELEASE : 0 0 0
RADP EXPENDITURE : 0 0 0
CUMULATIVE EXPENDITURE : 11523 PHYSICAL PROGRESS : 13 %