PROJECT DETAILS


IMPLEMENTING AGENCY : Khulna WASA
PROJECT CODE :
NAME OF PROJECT : Khulna Water Supply Project
APPROVAL STATUS : Approve DATE OF APPROVAL:
2010-02-14
NAME OF PD :
OBJECTIVES 1 : Study on Ground water.
OBJECTIVES 2 : Improvement of organizational system.
OBJECTIVES 3 : The conducting detail study to proper investment project.
PROJECT LOCATION : Khulna City.
REPORTING PERIOD : 2011-01-01 to 2017-06-30
STARTING DATE : 2011-01-01 COMPLETION DATE : 2017-06-30
FINANCIAL YEAR : 2012 SOURCE OF FUND : GOB and ADB
: TOTAL GOB PA
PROJECT COST : 255834 75043 18091
FINANCIAL INFORMATION
: TOTAL GOB PA
ADP ALLOCATION : 4791 3000 1791
ADP RELEASE : 2724 1477 1247
ADP EXPENDITURE : 1271 24 1247
RADP ALLOCATION : 0 0 0
RADP RELEASE : 0 0 0
RADP EXPENDITURE : 0 0 0
CUMULATIVE EXPENDITURE : 3171 PHYSICAL PROGRESS : 33 %
COMMENTS :