::LGD::

PROJECT DETAILS


IMPLEMENTING AGENCY : Local Government Engineering Department
PROJECT CODE : 5025
NAME OF PROJECT : District Towns Infrastructure Development Project-Revised
APPROVAL STATUS : Approve DATE OF APPROVAL:
2008-08-28
NAME OF PD : Md. Abdus Salam Mondal
OBJECTIVES 1 : a) Development of Infrastructure to meet the demand of basic needs; b) Development of Environment
OBJECTIVES 2 : c) Improvement of Communication system along with generation of short term and long term employment through Infrastructure Development, re-construction and rehabilitation
OBJECTIVES 3 : d) Preparation of Master Plan.
PROJECT LOCATION : 43 Paurashava
REPORTING PERIOD : 2004-07-01 to 2014-06-30
STARTING DATE : 2004-07-01 COMPLETION DATE : 2014-06-30
FINANCIAL YEAR : 2013 SOURCE OF FUND : GOB
: TOTAL GOB PA
PROJECT COST : 21035 21035 0
FINANCIAL INFORMATION
: TOTAL GOB PA
ADP ALLOCATION : 4408 4408 0
ADP RELEASE : 2947 2947 0
ADP EXPENDITURE : 2740 2740 0
RADP ALLOCATION : 0 0 0
RADP RELEASE : 0 0 0
RADP EXPENDITURE : 0 0 0
CUMULATIVE EXPENDITURE : 19366 PHYSICAL PROGRESS : 96 %
COMMENTS :

Khandker Mosharraf Hossain

Abdul Malek

Last Update Date

2017-12-18