PROJECT DETAILS


IMPLEMENTING AGENCY : Local Government Engineering Department
PROJECT CODE : 5027
NAME OF PROJECT : Construction of Flyover Bridge in Dhaka City (Mogbazar-Mouchak (Integrated) Flyover).
APPROVAL STATUS : Approve DATE OF APPROVAL:
2011-03-08
NAME OF PD : Nazmul Alam
OBJECTIVES 1 :
OBJECTIVES 2 :
OBJECTIVES 3 :
PROJECT LOCATION : Dhaka
REPORTING PERIOD : 2011-01-01 to 2014-12-31
STARTING DATE : 2011-01-01 COMPLETION DATE : 2014-12-31
FINANCIAL YEAR : 2013 SOURCE OF FUND : GOB, SFD, OFID
: TOTAL GOB PA
PROJECT COST : 77270 20047 20047
FINANCIAL INFORMATION
: TOTAL GOB PA
ADP ALLOCATION : 15500 2500 13000
ADP RELEASE : 9275 1875 1875
ADP EXPENDITURE : 9047 1872 7175
RADP ALLOCATION : 0 0 0
RADP RELEASE : 0 0 0
RADP EXPENDITURE : 0 0 0
CUMULATIVE EXPENDITURE : 14282 PHYSICAL PROGRESS : 25 %
COMMENTS :

Khandker Mosharraf Hossain

Abdul Malek

Last Update Date

2017-08-16