PROJECT DETAILS


IMPLEMENTING AGENCY : Local Government Engineering Department
PROJECT CODE : 5028
NAME OF PROJECT : Shama Shundery Canal Development in Rangpur Project
APPROVAL STATUS : Approve DATE OF APPROVAL:
2011-03-30
NAME OF PD : Md. Shafiqul Islam Akhand
OBJECTIVES 1 :
OBJECTIVES 2 :
OBJECTIVES 3 :
PROJECT LOCATION : Rangpur
REPORTING PERIOD : 2011-03-01 to 2014-06-30
STARTING DATE : 2011-03-01 COMPLETION DATE : 2014-06-30
FINANCIAL YEAR : 2013 SOURCE OF FUND : GOB
: TOTAL GOB PA
PROJECT COST : 2485 2485 0
FINANCIAL INFORMATION
: TOTAL GOB PA
ADP ALLOCATION : 1102 1102 0
ADP RELEASE : 827 827 0
ADP EXPENDITURE : 827 827 0
RADP ALLOCATION : 0 0 0
RADP RELEASE : 0 0 0
RADP EXPENDITURE : 0 0 0
CUMULATIVE EXPENDITURE : 2210 PHYSICAL PROGRESS : 94 %