PROJECT DETAILS

IMPLEMENTING AGENCY : Chittagong WASA
PROJECT CODE :
NAME OF PROJECT : Karnaphuli Water Supply Project
APPROVAL STATUS : Approved DATE OF APPROVAL: 2011-02-08 NAME OF PD:
OBJECTIVES 1 : To Supply 136 MLD potable water in the city of Chittagong.
OBJECTIVES 2 :
OBJECTIVES 3 :
PROJECT LOCATION : Chittagong city.
REPORTING PERIOD : September 2013
STARTING DATE : 2006-03-01 COMPLETION DATE : 2013-12-31
FIANCIAL YEAR : 2013-2014 SOURCE OF FUND : GOB & JICA
   
TOTAL
GOB
PA
PROJECT COST :
151,018.84
50369.32 + 1500.00 99,149.52
FINANCIAL INFORMATION
   
TOTAL
GOB
PA
RADP ALLOCATION :
ADP ALLOCATION : 50027.00 10000.00 40027.00
RADP RELEASE :
ADP RELEASE : 6428.00 5000.00 1428.00
RADP EXPENDITURE :
ADP EXPENDITURE : 1600.00 172.00 1428.00
CUMULATIVE EXPENDITURE : 80746.00 PHYSICAL PROGRESS : 57.00%